Middle Road Project

***UPDATE***  The State and their contractors have changed their timelines on this project.  Although they have now begun, it appears they are projecting through July 21st as an end date at this time.

The Maine Department of Transportation is scheduled to complete overlay and drainage improvements on Route 9/Middle Road, from approximately the turnpike overpass to Route 126.  They are scheduled to begin setting up for the project on Monday, June 5th and are scheduled to begin the work on Thursday, June 8th.  It is estimated they will complete the project in approximately 1 month.  Residents and property owners adjacent to this project may contact Ihsan.Rbeat@maine.gov, for information connected to this project.